Application Details

Locality

Pittsylvania County

Application Type

VWP Individual Permit Application

Facility Name

MVP Southgate Amendment Project

Agency Name

DEQ

Application Number

25-0752

Application Description

Processing steps for the issuance of VWP individual permits that are not related to linear transportation or water withdrawals.

Agent Name

Burns & McDonnell Engineering Company, Inc.

Application Process Timeline

*Application Process Timeline and Details initially display required process steps for application completion. Optional steps are displayed as they are included in the process. The original target date does not include the optional steps. Revised Target date includes the additional time of optional steps included.

Target Completion Date

9/21/2025

Revised Target Date

11/21/2025

Rotate phone orientation icon Rotate mobile device to view this Application's Process Timeline

Application Process Details

Step SubStep Description Target Start Date Target End Date Actual Start Date Actual End Date Step Assignee Target Duration Actual Duration Process Status
Application Review VDEQ Application Review Once received, VDEQ is allotted 15 calendar days to review an application for a VWP individual permit and to determine if it is administratively complete per applicable regulations. 04/18/2025 05/03/2025 04/18/2025 05/01/2025 VDEQ 15 Days 13 Days Complete
Application Review Applicant Additional Information Response The applicant must respond to the entirety of VDEQ's additional information request. A subsequent request for information by VDEQ may be necessary. 05/03/2025 05/18/2025 05/01/2025 05/30/2025 Applicant 15 Days 29 Days Complete
Application Review VDEQ Additional Information Review This step is initiated when an applicant submits information or responds to VDEQ's first additional information request. VDEQ reviews the applicant's response and may request additional information. 05/30/2025 06/14/2025 05/30/2025 06/12/2025 VDEQ None 13 Days* Complete
Application Review Applicant Subsequent Additional Information Response The applicant must respond to all VDEQ additional information requests in order to complete the Application Review step. 06/12/2025 06/27/2025 06/12/2025 07/17/2025 Applicant None 35 Days* Complete
Application Review VDEQ Additional Information Review This step is initiated when an applicant submits information or responds to VDEQ's first additional information request. VDEQ reviews the applicant's response and may request additional information. 05/30/2025 06/14/2025 07/17/2025 VDEQ None 1 Days* In Progress
Application Ready for Coordination with VMRC, VDH, VDCR, VDWR Request Comments from Agencies VDEQ requests comments from each of the four agencies. 05/18/2025 05/19/2025 04/21/2025 04/23/2025 VDEQ 1 Days 2 Days Complete
Coordination with VDCR VDCR Consultation VDEQ shall consult with and give full consideration to the written recommendations of VDCR. VDCR may request further information from the applicant, either directly or via VDEQ. VDCR may submit written comments on proposed permits within 45 calendar days after notification, after which VDCR has no further opportunity to comment. 05/19/2025 07/03/2025 04/23/2025 06/03/2025 VDCR 45 Days 41 Days Complete
Coordination with VDCR VDEQ Evaluation of VDCR Recommendations VDEQ evaluates the VDCR recommendations and may apply special permit conditions accordingly. 07/03/2025 07/18/2025 06/03/2025 06/03/2025 VDEQ 15 Days 0 Days Complete
Coordination with VDWR VDWR Consultation VDEQ shall consult with and give full consideration to the written recommendations of VDWR. VDWR may request further information from the applicant, either directly or via VDEQ. VDWR may submit written comments on proposed permits within 45 days after notification, after which VDWR has no further opportunity to comment. 05/19/2025 07/03/2025 04/23/2025 VDWR 45 Days 86 Days In Progress
Coordination with VDWR VDEQ Evaluation of VDWR Recommendations VDEQ evaluates the VDWR recommendations and may apply special permit conditions accordingly. 07/03/2025 07/18/2025 VDEQ 15 Days Not Started Not Started
Coordination with VMRC VMRC Consultation VDEQ shall consult with and give full consideration to the written recommendations of VMRC. VMRC may request further information from the applicant, either directly or via VDEQ. VMRC may submit written comments on proposed permits within 45 days after notification, after which VMRC has no further opportunity to comment. 05/19/2025 07/03/2025 04/23/2025 06/09/2025 VMRC 45 Days 47 Days Complete
Coordination with VMRC VDEQ Evaluation of VMRC Recommendations VDEQ evaluates the VMRC recommendations and may apply special permit conditions accordingly. 07/03/2025 07/18/2025 06/09/2025 06/09/2025 VDEQ 15 Days 0 Days Complete
Coordination with VMRC Applicant Response to VDEQ/VMRC The applicant must respond to information requests from VDEQ or VMRC. 06/09/2025 06/24/2025 06/09/2025 Applicant None 39 Days* In Progress
Coordination with VDH VDH Consultation VDEQ shall consult with and give full consideration to the written recommendations of VDH. VDH may request further information from the applicant, either directly or via VDEQ. VDH may submit written comments on proposed permits within 45 days after notification, after which VDH has no further opportunity to comment. 05/19/2025 07/03/2025 04/23/2025 05/19/2025 VDH 45 Days 26 Days Complete
Coordination with VDH VDEQ Evaluation of VDH Recommendations VDEQ evaluates the VDH recommendations and may apply special permit conditions accordingly. 07/03/2025 07/18/2025 05/19/2025 05/30/2025 VDEQ 15 Days 11 Days Complete
Individual Permit Decision VDEQ Development of Draft Permit Decision VDEQ develops a draft individual permit and public notice for its tentative decision to issue an individual permit. 05/19/2025 07/18/2025 VDEQ 60 Days Not Started Not Started
Individual Permit Decision Applicant Review of Draft Permit Every draft VWP individual permit, with the exception of a VWP Emergency Virginia Water Protection Permit, shall be given public notice that must be published within 14 days of the applicant's receipt of a draft VWP permit, or the 120-day VWP individual permit processing timeframe will be suspended until such publication. 07/18/2025 08/01/2025 Applicant 14 Days Not Started Not Started
Individual Permit Decision Public Comment - Draft Permit Decision A draft individual permit is subject to a 30-day public comment period prior to issuance by VDEQ. 08/01/2025 09/05/2025 VDEQ 35 Days Not Started Not Started
Individual Permit Decision Final Permit Decision After the applicable public comment period(s) have closed, VDEQ makes the final permit decision. 09/05/2025 09/21/2025 VDEQ 16 Days Not Started Not Started

Application Processing Days

Below are the total number of days that this application was with each agency for processing or with the applicant to complete their required steps.

VDEQ

38 Days

VDCR

41 Days

VDWR

86 Days

VMRC

47 Days

VDH

26 Days

Applicant

68 Days